A disused atrium at Ayr Railway Station is set to reopen after South Ayrshire Council officers approved plans to refurbish the space and bring it back into use.

Network Rail applied earlier this year for listed building consent for work at the end of platforms one and two. The project is intended to improve passenger movement, particularly during busy periods, while supporting safety and restoring features of the Victorian station.

Why the atrium has been closed

Ayr station opened in 1885 and is known for its glazed canopies. The adjacent hotel was largely destroyed by fire in September 2023, affecting the station as well. Network Rail said the station was not irreversibly damaged and that many traditional features remained.

The hotel had already been in poor physical condition since the early 2010s. Temporary measures were introduced to protect the building and passengers, with further measures put in place after the fire so the station could continue operating safely.

Network Rail said those measures affected the passenger experience and the character of the listed building. The atrium itself has been unused for several years because of its proximity to the former hotel, which was considered dangerous before demolition work began.

What the approved work includes

The proposals will replace the atrium floor with Vebroflex Bounce UV resin flooring and install temporary timber hoarding against the interior walls. Broken roof glazing will be repaired or replaced, while the glazed walls will be cleaned and stickers removed.

Existing automatic doors described in the application as dilapidated will be removed. The refurbished space will include new seating, vending machines and replacement customer information screen boards.

Heritage lighting will be refurbished, with missing units replaced by matching fittings. Where possible, broken units held in storage will be reused. Metalwork, including columns and roof trusses, will be cleaned and repainted on a like-for-like basis.

The station’s roof canopies were previously changed from glazing to polycarbonate sheets. Any replacements included in this scheme will use the same material.

Wider station regeneration has no timetable

Network Rail said the atrium project would bring a disused area back into use and highlight traditional station features that are currently obscured. The company also said the proposals were designed to fit the character of a Victorian railway station that remains operational in the 21st century.

Long-term plans are being developed to regenerate the wider station complex, but planning documents state that there is currently no timeframe for delivering a full regeneration scheme. Funding has, however, been secured for the atrium work.

Council decision documents said the approved works would restore traditional features while making the space functional as part of a modern, operational railway station. Officials recorded that there were no objections to the principle of the proposals.