Scaffolding is being removed from Ayr Sheriff Court as more than two years of safety and repair work on the building nears completion.

The work began after masonry fell from the court in June 2024, prompting safety measures around the building. The Scottish Courts and Tribunals Service (SCTS) then commissioned an intrusive fabric survey to examine the condition of the stonework.

Why the scaffolding was installed

The survey identified problems with the stone’s integrity, largely linked to the age of the building. Scaffolding and protective netting were installed across the front façade as a precaution, helping to make the court safe and prevent further stone from falling.

Repairs have now been carried out and the scaffolding is being taken down outside as the work progresses towards completion.

Cost and revised completion date

A Freedom of Information request by the Ayr Advertiser found that renovation costs had reached £262,898 by December last year.

The first phase cost £198,753 between July 2024 and July 2025. It included the stonework survey, specialist consultant costs and scaffolding. A second phase, covering stone repairs and associated scaffolding, cost £64,145 from July to December 2025.

The SCTS initially anticipated that the project would be completed by the end of May this year. That target was later revised to October because the work was taking longer than expected.

“We would like to thank people for their patience while this important work is undertaken.”

The SCTS said the building work is now nearing completion, with the removal of the external scaffolding marking the latest stage of the repairs.