Businesses in Ayr town centre are being called to a meeting about proposed cycle lanes and wider street changes, with concerns raised about parking, customer access, deliveries and the effect on the town centre.

The meeting is scheduled for Tuesday, September 29. Its time and location will be sent privately to business owners and managers who contact the organisers.

The discussion follows concerns from businesses and residents about proposals being developed through South Ayrshire Council’s £19.9 million Accessible Ayr project. The project is intended to improve walking, cycling, traffic movement and public transport links in Ayr and nearby areas.

What the proposed Ayr changes include

The designs under consideration include changes around the Fort Street, Fullarton Street and Sandgate junction, along with alterations on Alloway Street.

Fort Street North, between Sandgate and Citadel Place, would become one-way northbound. Signalised crossings would also be changed, while a bi-directional cycleway is proposed on the east side of Alloway Street.

Under the plans, disabled parking spaces and loading bays would move to the west side of Alloway Street. A signalised crossing would be relocated further north, closer to the High Street.

The proposals are part of a project expected to continue beyond the planned 2028 completion of the Burns Statue Square project. The designs remain largely similar to those approved at stage three.

Businesses raise concerns over revised plans

Tempura, an Ayr business, said local businesses and residents had previously joined opposition to cycle lanes on Alloway Street and Sandgate. The business said the revised plans still included the lanes, despite a public announcement that they would not.

“Back in January many local businesses and residents came together to oppose the proposed cycle lanes on Alloway Street and Sandgate.”
“Following the backlash, South Ayrshire Council publicly announced that the redesigned plans would NOT include these cycle lanes.”
“Fast forward to this week, and the revised plans STILL include them!”

Tempura said there were serious concerns about the removal of parking, customer access, deliveries and the possible impact on an already struggling town centre.

“We opposed these plans in January and we will all oppose them again!”

Councillor Alec Clark said concerns raised by businesses earlier in the year had not been properly reflected in the report considered by the council’s cabinet.

Further consultation planned

A report considered by the cabinet on September 22 recommended further design work, additional consultation and changes to the project’s delivery plan. The recommendations also proposed extending the study areas for the first two phases while keeping Accessible Ayr within the Ayr Town Centre Framework.

The cabinet divided the project into two phases in August 2024. The first phase covers areas mainly south of the River Ayr, while the second covers areas to the north.

South Ayrshire Council’s latest recommendations call for more consultation before the next stages of the project are confirmed. The forthcoming business meeting will provide an opportunity for local owners and managers to discuss the proposed changes privately with organisers.